Short Term Plans
- Development of infrastructure at Mangalore facilities for receipt, unloading, handling, blending, storage and grinding of Haemetite Ore sourced from different agencies.
- Modification of the existing flow sheet for usage of different types of Ore.
- Upgradation of filtration system.
- Mechanisation of un-loading system at Mangalore port for receipt and handling of raw materials received through ships.
- Pulvarised coal dust injection system in Blast Furnace unit.
- Development of Chikkanayakanahalli Mines.
- Contract mining and Pelletisation.
- Installation of Additional Pig casting machines (PCM) at Blast furnace unit to improve productivity.
Long Term Plans
- 3 Lakh tonne capacity Coke Oven Plant at Mangalore
- Permanent Railway siding at Mangalore for handling raw materials received through Railways.
- Upgradation of Pellet Plant capacity from 3.5 to 4.3 Million Tonnes
- Ductile Iron and spun Pipe Project
- ECO-tourism
Expansion and Diversification Measures
- Development of Barsua Iron Ore Deposits in Orissa
- Mining operations at Chiria/Jharkhand/Taldi areas
- Taking over of Kalinga Iron Works, Orissa
|
|